说明:双击或选中下面任意单词,将显示该词的音标、读音、翻译等;选中中文或多个词,将显示翻译。
您的位置:首页 -> 词典 -> 无缝连续施工
1)  jointless and continuous construction
无缝连续施工
2)  jointless construction
无缝施工
1.
Practice of the jointless construction technology of the super-long concrete structure;
超长混凝土结构无缝施工实践
2.
On the setting of the expansion-reinforcing band in the over-long concrete structure jointless construction
超长混凝土结构无缝施工中膨胀加强带的设置
3.
From three aspects: design mechanism,shrinkage-compensating concrete and mix proportion design jointless construction plan of concrete is introduced.
从设计机理、补偿收缩混凝土、混凝土配合比设计三方面对无缝混凝土施工方案进行了介绍,详细地阐述了大体积混凝土结构无缝施工的技术措施,以完善大体积混凝土结构无缝施工技术。
3)  seamless construction
无缝施工
1.
The application of concrete seamless construction technology;
混凝土无缝施工技术应用
2.
The technology application of underground steel concrete seamless construction in winter;
冬期地下室钢筋混凝土无缝施工技术应用
3.
The constructing methods of expanding concrete and strengthening belt in UEA seamless construction are elaborated in detail,so as to reduce the constructing period and project cost.
分析了UEA无缝施工技术的优点,简述了后浇带技术方案的施工质量缺陷,探讨了UEA无缝施工技术原理,详细地阐述了UEA无缝施工中膨胀混凝土和膨胀加强带的施工做法,从而缩短工期,降低工程成本。
4)  non-joint construction
无缝施工
1.
This paper analyzes existing developing condition of concrete structure design,introduces after-pouring joint construction and non-joint construction method,compares their characteristics,summarizes their advantages and disadvantages,and points out that people should take reasonable choice according to concrete engineering condition to ensure construction quality.
分析了混凝土结构设计工艺的发展现状,介绍了后浇缝施工和无缝施工的方法,并比较了二者的特点,总结了二者具有的利弊点,指出实际应用中应根据工程具体情况,合理选择,确保工程质量。
5)  continuous construction
连续施工
1.
Study on continuous construction of Jinghong hydropower station RCC dam in high temperature;
景洪电站高气温条件下大坝碾压混凝土连续施工研究
2.
The continuous construction of the Basecourse and the surface of the Lime-fly-ash Macadam is a new method that can accelerate the overall construction process, shorten the time limit for the project and further develop new characteristics of the Lime-fly-ash material.
二灰碎石基层与面层连续施工是加快施工进度、缩短工期,进一步挖掘出二灰材料独特性质的新方法,本文从基层是否有足够的强度来抵御面层连续施工时机械对其结构的破坏和施工工艺的合理选择两个方面阐述二灰碎石基层与面层能够连续施工原因。
3.
Using cement hydration mechanism and gradation composition principle,design methods of anti-cracks base were put forward with expansive cement and skeleton and dense structure gradation;technologies of continuous construction of two layers and saw cracks in advance were used.
针对我国水泥稳定半刚性基层存在裂缝的突出问题,研究水泥水化机理和级配组成原理,提出了微膨胀水泥+骨架密实级配的基层防裂设计方法,提出了双层连续施工+预锯缝的施工工艺。
6)  non layer joints construction
无层缝施工
补充资料:混凝土施工缝


混凝土施工缝
concrete construction joint

hunningtu sh一gongfeng混凝土施工缝(eonerete construetion joint) 先后浇筑的混凝土,其间歇时间超过混凝土凝结时间所形成的接缝。浇筑混凝土应连续进行,如必须间歇,其间歇时间应尽量缩短,并在前层混凝土凝结以前,将次层混凝土浇筑完毕。超过允许的间歇时间,以致用振捣器也难以使新浇的混凝土与先浇的混凝土结合成整体时,结合面即形成施工缝。与混凝土浇筑区段一平面平行的施工缝称水平施工缝,与浇筑区段平面垂直的施工缝称垂直施工缝。 混凝土浇筑允许的间歇时间,即为混凝土凝结时间,依所用水泥品种和凝结条件而异,日本及前苏联等国家都有明确规定,中国规范规定的混凝土凝结时间见表。 浇筑混凝土的间歇时间…攀叮泣 注:1.表列数值包括混凝土运输和浇筑时间;2.当掺有 促凝或缓凝剂时,最大间歇时间需经试验确定。 混凝土施工缝是混凝土结构的薄弱环节,处理不好,会引起结构开裂、漏水及影响结构耐久性,重者甚至危及结构安全。因此,通常在混凝土结构施工方案中,应根据结构类型、浇筑数量和浇筑条件,对施工缝的留设位置、施工缝型式及继续浇筑混凝土时的技术处理等,都预先予以确定。 施工缝留设位置一般留在结构受剪力较小,且便于施工的部位。各类结构的留设位置为:(1)柱子的施工缝留设在基础的顶面,梁或吊车梁牛腿的下面、吊车梁的上面、无梁楼板柱帽的下面;(2)深度大的梁,其施工缝留设在与其相连接板底面以下20~3omm处,当板下有托梁时,则应留设在托梁底下;(3)单向板的施工缝可留设在平行于板的短边的任何位置;(4)有主次梁的楼板,宜顺着次梁方向浇筑,其施工缝应留设在次梁跨度中间1/3范围内;(5)双向受力楼板、拱壳、斗仓、蓄水池、设备基础及其他复杂的结构,其施工缝的位置应按设计要求留置,一般斗仓可留设在漏斗根部及上部,或漏斗与仓壁的交接处;地坑和水池应留设在坑壁,距坑底30~50cm范围内;(6)承受动力作用的设备基础一般不设施工缝,如必须留设时,应征得设计单位同意,一般可在互不相依的两台设备和输送辊道支架之间留设垂直施工缝;(7)当在设备基础的地脚螺栓范围内留设施工缝时,水平施工缝应留设在距螺栓底下大于150mm处(直径小于3Omm的螺栓,水平缝可留设于螺栓埋入部分总长的3/4处),垂直施工缝应留设在距螺栓中心线25omm以外并小于5倍螺栓直径处。 施工缝型式对无防水要求的构筑物可采用平直的施工缝;对有防水要求的结构物应采用企口缝、V形缝或平缝加止水板。
说明:补充资料仅用于学习参考,请勿用于其它任何用途。
参考词条