1) mud-filled bag embankment
充填管袋筑坝
2) filled geotube
充填管袋
3) geo-tube filling
管袋充填
1.
For the construction of a freshwater reservoir on the beach of the Yangtze River Estuary for the prevention of saltwater intrusion, a field experiment was performed on the techniques for bank construction with spoil, including geo-tube filling, spoil dredging, sun-dried spoil rolling, etc.
试验结果表明,细粒含量高的土体的充填和吹填工艺不能满足潮汐施工要求与正常工期要求,粉细砂可满足管袋充填的潮汐施工的安全要求,弃土可采用翻晒干填碾压工艺满足坝体质量与工期要求。
4) sucking sand pipe bag dam
充沙管袋坝
5) filling geotube
土工充填管袋
1.
The technique of constructing a dam with filling geotube is one of the importantstructure arts in coastal protection engineering and in enclosing tideland forcultivation engineering along the estuary and the sea.
土工充填管袋筑坝技术是河口、沿海等海岸防护工程、围海造陆工程中采用的一种重要的建筑技术,充填管袋堤坝建筑物也是水利、海岸工程中的一种重要建筑物型式。
2.
The technique of constructing a dam with filling geotube is one of the important structure arts in coastal protection engineering and in enclosing tideland for cultivation engineering along the estuary and the sea.
土工充填管袋筑坝技术是河口、沿海等海岸防护工程、围海造陆工程中采用的一种重要的建筑技术,充填管袋堤坝建筑物也是水利、海岸工程中的一种重要建筑物型式。
补充资料:钢铁厂矿山利用尾矿筑尾矿坝
钢铁厂矿山利用尾矿筑尾矿坝
钢铁厂矿山利用尾矿筑尾矿坝
说明:补充资料仅用于学习参考,请勿用于其它任何用途。
参考词条